Your ERP go-live checklist for a Qatar business

The specific checks worth doing in the week before cut-over, drawn from implementations that went smoothly and ones that did not.

 · 1 min read

Go-live is not a switch, it is a sequence. Here is what to confirm in the week before, and in the days immediately after.

Data

  • Trial balance matches your old system to the fils.
  • Stock quantity and valuation reconcile per warehouse — quantity alone is not enough.
  • Open documents are loaded: unpaid sales and purchase invoices, live purchase orders, pending deliveries, outstanding advances.
  • A sample of customers, suppliers and items spot-checked by your own team.

Documents

  • Bilingual print formats produced for tax invoices, delivery notes, purchase orders, quotations and payslips.
  • Numbering series agreed and continuing sensibly from the old system.
  • A test print of each document reviewed by whoever signs them.

Payroll

  • Parallel payroll run against the last paid period, compared line by line.
  • WPS salary file generated and checked against the layout your bank accepts.
  • Leave balances loaded.

Access

  • Every user has an account with the right role — and only the right role.
  • Approval workflows tested by the people who will approve, not by us.
  • Someone other than one person knows the administrator credentials.

Cut-over

  • The date lands on a month-end, ideally a year-end.
  • The old system is available read-only, not switched off.
  • Everyone knows who to call in week one.

First month-end

The real test is not day one, it is the first close. Book the time for it. We are on-site through it, because that is when the questions that matter surface — and answering them properly is what makes month two uneventful.