Your ERP go-live checklist for a Qatar business
The specific checks worth doing in the week before cut-over, drawn from implementations that went smoothly and ones that did not.
·
1 min read
Go-live is not a switch, it is a sequence. Here is what to confirm in the week before, and in the days immediately after.
Data
- Trial balance matches your old system to the fils.
- Stock quantity and valuation reconcile per warehouse — quantity alone is not enough.
- Open documents are loaded: unpaid sales and purchase invoices, live purchase orders, pending deliveries, outstanding advances.
- A sample of customers, suppliers and items spot-checked by your own team.
Documents
- Bilingual print formats produced for tax invoices, delivery notes, purchase orders, quotations and payslips.
- Numbering series agreed and continuing sensibly from the old system.
- A test print of each document reviewed by whoever signs them.
Payroll
- Parallel payroll run against the last paid period, compared line by line.
- WPS salary file generated and checked against the layout your bank accepts.
- Leave balances loaded.
Access
- Every user has an account with the right role — and only the right role.
- Approval workflows tested by the people who will approve, not by us.
- Someone other than one person knows the administrator credentials.
Cut-over
- The date lands on a month-end, ideally a year-end.
- The old system is available read-only, not switched off.
- Everyone knows who to call in week one.
First month-end
The real test is not day one, it is the first close. Book the time for it. We are on-site through it, because that is when the questions that matter surface — and answering them properly is what makes month two uneventful.